October 22, 2026
The building at 1104 Decatur Street, where Margaritaville used to be, has a first floor split in two, bars on two levels, a courtyard and a long upstairs balcony. On Oct. 29 it opens as The Cocktail Hour, a 30-week pop-up bar from the Jewel of the South team. A Turkey and the Wolf spinoff called And the Wolf takes the other side of the ground floor, Axios New Orleans reported.
The 1100 block of Decatur is the stretch of the Sewerage and Water Board project that crews finished first. Two blocks upriver, the 900 block still has most of its surface work ahead of it. Lower Decatur is reopening one block at a time, and new businesses are arriving in the same order the pavement went down.
The project covers the 900, 1000 and 1100 blocks of Decatur and the 600 block of St. Peter. The underground part is finished. In its Oct. 6, 2026 construction update, SWBNO lists sewer, drainage and water at 100% on every block. What's left is the street and sidewalk surface.
| Block | Cross streets | Pavement, Oct. 6 | Sidewalks, Oct. 6 | Estimated completion |
|---|---|---|---|---|
| 600 St. Peter | Chartres to Royal | 100% | 100% | September 2026 |
| 1100 Decatur | Gov. Nicholls to Ursulines | 100% | 100% | Summer 2026 |
| 1000 Decatur | Ursulines to St. Philip | 96% | 85% | Fall 2026 |
| 900 Decatur | St. Philip to Dumaine | 15% | 0% | Fall 2026 |
Compare that with six weeks earlier. SWBNO's Aug. 25 update had the 900 block at 0% pavement and 0% sidewalks, and the 1000 block at 0% sidewalks. So between late August and early October, the 1000 block went from no finished sidewalk to most of it, and the 900 block started getting pavement. Both blocks still show "Fall 2026" as their estimate, which is SWBNO's projection and not a date.
The 1100 block was the first section where crews finished the full repaving. New Orleans CityBusiness reported on Aug. 21 that paving was complete there, including the Gov. Nicholls and Ursulines intersections. SWBNO notes that lane striping on the finished blocks was delayed by weather and scheduling. Even so, the October update lists the 1100 block as open to pedestrians and the 600 block of St. Peter as open to vehicles.
The blocks that are finished or nearly finished are also the ones where storefronts turned over during the work.
The Cocktail Hour is the first big new tenant on these blocks. It is also temporary. Axios describes the residency as 30 weeks, with the design changing over that time to follow five of what managing partner John Stubbs calls "New Orleans' cultural seasons." Thirty weeks from Oct. 29 runs into late May 2027, which puts the residency in place for the busy months from the holidays through spring festival season. The plan includes live music and a rotating lineup of guest bartenders.
With the downriver end finished, the remaining work is concentrated between St. Philip and Dumaine. SWBNO's Oct. 6 update says crews are forming the lake side of the 900 block roadway for the next concrete pour, a pour it said depended on weather from a Gulf storm. The update also says work is happening at the same time on N. Peters, and that restoration work had the intersection closed for about three weeks. Fox 8 also cited SWBNO's dashboard on Oct. 1: the 1000 block was nearly complete, and most of the remaining work was on the 900 block.
For anyone walking this stretch, some rules changed over the summer. On July 17, 2026, WGNO reported on a court-approved agreement between SWBNO and a group of French Quarter businesses. Under its terms, fencing comes down where work isn't active, businesses get at least 72 hours' notice before new or extended street closures, and affected businesses are exempt from water disconnections. WGNO also reported that the agreement bars closing streets for sidewalk repairs. NOLA.com listed the businesses behind the suit. Most are names you'd recognize from these blocks, including Original French Market Restaurant & Bar, Frank's Restaurant, Minnow Jewelry Bar, Sidney's, the Abbey Bar, Turtle Bay, Cornet and Huge Ass Cantina. By Oct. 1, Fox 8 reported that fencing had come down in some places and parts of Decatur had reopened.
Some businesses are still dealing with problems. On Oct. 5, Fox 8 reported that Original French Market Restaurant & Bar had a ceiling collapse, cracks and buckling, and had closed its balcony for safety. The report did not say the restaurant itself had closed.
The French Market District holds its free Boo Carre Halloween Haunt on Saturday, Oct. 24, from 11 a.m. to 4 p.m. in Dutch Alley. The program includes live music, children's activities, a Spooky Second Line and trick-or-treating. Children in costume can get a free Boo Carre tote bag at the information booth while supplies last, according to the French Market District.
The event page places the starting point in the 900 block of N. Peters, the same block number where SWBNO reported concurrent work in early October. If you're taking kids, check SWBNO's latest construction update before you go. Coming from the downriver side over the finished 1100 block may be the easier walk.
The rest of the fall's new places are spread a few blocks away from the construction zone.
One more change on the Quarter's edge: Effervescence, the champagne-and-caviar bar on Rampart Street, closed at the end of August, per Where Y'at. Brenna Sanders and Evan Ingram, the chefs who ran its kitchen, have taken over the space at 1036 N. Rampart St. as The Crustacean Club, which focuses on Gulf seafood and still serves champagne.
Once Boo Carre is over, the French Market District calendar lists three more events through December:
Those dates fall in the same window SWBNO gave for finishing the 1000 and 900 blocks. If the fall estimate holds, the Farm to Table weekend could be the first French Market event in about a year with all of lower Decatur open, but SWBNO hasn't set a date. Its next construction update will show whether the 900 block's pavement has moved past 15%.
If you own property on one of these blocks and are wondering how the finished street affects the timing of a sale or lease, Team Right Side works in the French Quarter every day and can go over your block with you. Contact us when you're ready to talk.
Stay up to date on the latest real estate trends.
Whether you’re buying, selling, investing, or leasing in New Orleans, Team Right Side brings the experience, local insight, and attention to detail needed to move forward with confidence. We create a thoughtful plan around your goals, manage the complexities along the way, and provide trusted guidance from the first conversation through closing.